Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
A. Send an email to quality assurance and copy the project team.
B. Call a meeting to hand off the deliverable to quality assurance.
C. Hold a conference call to a review the next deliverable with the project team.
D. Send an email to the project sponsor and copy the project team.