CompTIA Project+ PK0-004 – Question260

A project manager has been experiencing resistance from a group of stakeholders.
With which of the following should the project manager consult to reduce friction going forward?

A.
Project scheduler
B. Project coordinator
C. Project sponsor
D. Project management office

Correct Answer: C