Which of the following is the BEST way for the PM to validate the assessment?
A. Ask the team for estimates, and review the project schedule and budget.
B. Ask the team to review the product scope and validate its impact on the schedule and quality.
C. Ask the team for estimates, and review the cost management plan.
D. Ask the team to perform a SWOT analysis, and validate the assessment.