– Project description
– Draft project timeline and schedule
– Rough milestones
– Draft project budget
– Draft resources required
– High-level risk review
Which of the following sections should be included in this document?
A. Business information
B. Full risk assessment results
C. Draft work breakdown structure
D. Full resource requirements