CompTIA Project+ PK0-004 – Question283

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?

A.
Communicate the change
B. Quality check
C. Implementation
D. Evaluate impact and justification

Correct Answer: D