CompTIA Project+ PK0-004 – Question285

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)

A.
Planned value
B. Schedule variance
C. Acceptable variance
D. Cost variance
E. Earned value

Correct Answer: DE