A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
– Project title description
– Preassigned resources
– Budget
– WBS
– Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
A. Project title and description
B. Preassigned resources
C. Budget
D. WBS
E. Measurable project objectives