CompTIA Project+ PK0-004 – Question299

Two companies have merged. Which of the following may impact the project manager's communication methods after the merger?

A.
Updates to issues logs
B. Increase in change requests
C. Changes to stakeholder requirements
D. Updates to the WBS

Correct Answer: C