CompTIA Project+ PK0-004 – Question301

A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?

A.
Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register

Correct Answer: B