Which of the following steps should the PM take to make the meetings more productive? (Choose two.)
A. Facilitate the meetings by adhering to the agenda.
B. Encourage interaction among team members during the meetings.
C. Ensure meetings minutes are accurately recorded.
D. Adjust the number of meetings.
E. Change the number of action items.
F. Schedule impromptu meetings when the SME is absent.