CompTIA Project+ PK0-004 – Question316 Given the information in the table below, which of the following is the total project cost? A. $40,000B. $70,000C. $95,000D. $120,000 Show Answer Hide Answer Correct Answer: B Post navigation CompTIA Project+ PK0-004 – Question315CompTIA Project+ PK0-004 – Question317