CompTIA Project+ PK0-004 – Question324

The anticipated funding level for an approved project was reduced. The sponsor has met with the project manager to identify several scope reductions. Which of the following is the NEXT step the project manager should take?

A.
Update the documentation.
B. Implement the change.
C. Close the project.
D. Evaluate the impact.

Correct Answer: D