A. Have the team members deny all change requests from this stakeholder
B. Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
C. Contact the key stakeholder to encourage the submission of written change requests
D. Request additional resources from the project team to complete the change requests from the key stakeholder