CompTIA Project+ PK0-004 – Question338 Which of the following resources outlines consequences of non-performance?A. Project sponsorB. Project teamC. CustomerD. Project management office Show Answer Hide Answer Correct Answer: D Post navigation CompTIA Project+ PK0-004 – Question337CompTIA Project+ PK0-004 – Question339