CompTIA Project+ PK0-004 – Question349 Which of the following documents will provide the MOST detailed information regarding the work a vendor will perform during a project?A. RFIB. SLAC. SOWD. PO Show Answer Hide Answer Correct Answer: C Post navigation CompTIA Project+ PK0-004 – Question348CompTIA Project+ PK0-004 – Question350