CompTIA Project+ PK0-004 – Question353

The following tasks are required to complete an IT project that is behind schedule:

Which of the following is the critical path?

A.
3, 2, 4
B. 4, 2, 3
C. 3, 2, 1, 4
D. 4, 1, 2, 3

Correct Answer: C