CompTIA Project+ PK0-004 – Question362

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.
Which of the following resources has the authority to authorize this change?

A.
Stakeholders
B. Scrum master
C. Project sponsor
D. Project team

Correct Answer: D