CompTIA Project+ PK0-004 – Question377

A project sponsor has requested documentation to determine the scheduled activities for a project that is running behind schedule. Which of the following documents should the project manager send to the sponsor to quickly identify the project activities?

A.
RACI
B. SWOT
C. SOW
D. WBS

Correct Answer: D