CompTIA Project+ PK0-004 – Question379 A project manager is reviewing project performance. Which of the following would be the BEST indicator of the total project cost?A. ACB. EACC. CPID. ETC Show Answer Hide Answer Correct Answer: B Post navigation CompTIA Project+ PK0-004 – Question378CompTIA Project+ PK0-004 – Question380