CompTIA Project+ PK0-004 – Question389

There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?

A.
Issue log
B. Project charter
C. Dashboard
D. Meeting minutes

Correct Answer: D