The managing director of a law firm has asked the project manager to create a scope statement for a new contract. Which of the following should be included in the scope statement? (Choose two.)

A.
Scope creep
B. Deliverables
C. Business requirements
D. Project schedule
E. Gate review
F. Key performance indicators

Correct Answer: BC