CompTIA Project+ PK0-004 – Question404 Which of the following is the first document issued during the procurement process in a project?A. POB. RFPC. RFID. RFQ Show Answer Hide Answer Correct Answer: C Post navigation CompTIA Project+ PK0-004 – Question403CompTIA Project+ PK0-004 – Question405