A project manager is collecting the number of hours, the resources, and the amount of money spent on hardware and software. Which of the following is MOST likely the purpose of collecting this information?

A.
Financial stability
B. Competitive advantage
C. Budget constraints
D. Expenditure tracking

Correct Answer: D