– Makes telephone calls to key stakeholders for urgent information
– Sends emails for routine information
– Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?
A. Prioritizing based on personal preferences
B. Tailoring the method based on message content
C. Adjusting the method based on confidentiality constraints
D. Demonstrating concern for technological factors