Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?
A. Incident response
B. Business continuity response
C. Resource change response
D. Schedule response
A. Incident response
B. Business continuity response
C. Resource change response
D. Schedule response