CompTIA Project+ PK0-004 – Question428

A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

Which of the following is the NEXT appropriate step for the project manager to take?

A.
Identify risk strategies for the realized events
B. Change the risk status to closed for 2 and 6
C. Consult the risk management plan
D. Update the issue log

Correct Answer: A