CompTIA Project+ PK0-004 – Question430

A project manager learns that a key team member is required to work on a different assignment within the next two weeks. In which of the following organizational structures does the project manager work?

A.
Projectized
B. Functional
C. Flat
D. Strong matrix

Correct Answer: B