CompTIA Project+ PK0-004 – Question439

The stakeholders who are available for the user acceptance test do not understand the project's requirements.
The tester is trying to identify who requested the feature, but there is no information available. Which of the following components is missing?

A.
RTM
B. Quality plan
C. Project schedule
D. SOW

Correct Answer: B