A project manager has set aside a contingency reserve for unforeseen communications. Which of the following types of communication is MOST likely to utilize this contingency reserve?
A. Impromptu meeting
B. Closure conference
C. Distributed printed media
D. Kickoff meeting
A. Impromptu meeting
B. Closure conference
C. Distributed printed media
D. Kickoff meeting