Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?
A. PO numbers
B. Cost baseline
C. Bill of materials
D. WBS codes
A. PO numbers
B. Cost baseline
C. Bill of materials
D. WBS codes