A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A. Submit a change request to the CCB.
B. Implement the change to the project.
C. Determine the impact of the requested change.
D. Update the schedule to accommodate the change.