CompTIA Project+ PK0-004 – Question464

A company recently went through a project requiring new equipment, new software, and retraining of personnel.
This is MOST likely a result of:

A.
an internal reorganization.
B. outsourcing.
C. a business process change.
D. resource allocation.

Correct Answer: C