Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?
A. A, C, D
B. A, C, E
C. A, D, E
D. B, C, E
A. A, C, D
B. A, C, E
C. A, D, E
D. B, C, E