CompTIA Project+ PK0-004 – Question474

A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having:

A.
dedicated resources.
B. interproject dependencies.
C. resource overallocation.
D. shared resources.

Correct Answer: D