CompTIA Project+ PK0-004 – Question499

Team members in a projectized organization are released at the end of a project and placed on the "bench".
Which of the following should the benched team members do NEXT?

A.
Find a new project.
B. Check in with a functional manager.
C. Report to the project manager.
D. Contact the project sponsor.

Correct Answer: B