CompTIA Project+ PK0-004 – Question505

A key team member found a new job and will be leaving in two weeks. Which of the following should the project manager do FIRST to minimize negative impacts to the project?

A.
Request a replacement from the project sponsor.
B. Contact human resources to initiate the termination process.
C. Involve the legal department for contract review.
D. Inform executive management about attrition.

Correct Answer: A