CompTIA Project+ PK0-004 – Question511

Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements.
Which of the following is the BEST way to expedite the projects?

A.
Project A can reduce the number of deliverables.
B. Project A can be crashed using Project B's resources.
C. Project B can have its resources leveled.
D. Project B can begin without Project A completing, therefore accepting future rework.

Correct Answer: B