A project team is creating a new product, and stakeholders are having a hard time understanding the product.
Which of the following should be sent to the stakeholders?
A. Printed sketches and potential uses
B. Memo outlining high-level requirements
C. Sponsor mandate for the product
D. Link to the project's intranet site to review status reports
Which of the following should be sent to the stakeholders?
A. Printed sketches and potential uses
B. Memo outlining high-level requirements
C. Sponsor mandate for the product
D. Link to the project's intranet site to review status reports