A new project manager is assigned in the middle of a seven-month project. The project is behind schedule, and there is only historical weekly cost data available.
Which of the following best practices should the project manager perform to assess project costs?
A. Review the SPI.
B. Create a burndown chart.
C. Ask the project sponsor for additional funding.
D. Perform a cost benefit analysis.