A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention.
Which of the following risks should the project manager accept? (Choose two.)
A. 1
B. 2
C. 3
D. 4
E. 5
F. 6