CompTIA Project+ PK0-004 – Question529

During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium.
Which of the following is the BEST course of action?

A.
Increase the contingency reserve.
B. Add the risks to the watch list.
C. Establish and monitor trigger conditions.
D. Assign the sponsor as the primary risk owner.