CompTIA Project+ PK0-004 – Question545

A sports event is coming to a local city, and the project manager for the event fears there might be violence if the local team wins.
Which of the following types of project activities would occur if the local team wins?

A.
Applying a risk mitigation plan
B. Securing appropriate funding
C. Implementing quality control measures
D. Changing the timeline

Correct Answer: A