A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources.
Which of the following impacts will MOST likely occur? (Choose two.)
A. Cost will increase.
B. Scope will increase.
C. Schedule will decrease.
D. Risk will decrease.
E. Budget will increase.
F. Quality will increase.