CompTIA Project+ PK0-004 – Question560

A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented.
Which of the following constraints has MOST likely been overlooked?

A.
Scope
B. Resources
C. Environment
D. Quality

Correct Answer: C