The vendor management team has requested all project managers to provide proof to back up complaints on vendor resolution delays.
Which of the following will provide this information?
A. Scope statement
B. Project plan
C. Action items
D. Issue log
Which of the following will provide this information?
A. Scope statement
B. Project plan
C. Action items
D. Issue log