CompTIA Project+ PK0-004 – Question566 Which of the following is the project phase when quality assurance occurs?A. PlanningB. ClosingC. ExecutionD. ScopingE. Initiation Show Answer Hide Answer Correct Answer: C Explanation: Reference: https://www.pm4dev.com/resources/free-e-books/5-project-quality-man… (9) Post navigation CompTIA Project+ PK0-004 – Question565CompTIA Project+ PK0-004 – Question567