Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:

Which of the following is MOST likely the cause?

A.
Predecessors not properly identified
B. Scope change
C. Retrospective in progress
D. Insufficient resources assigned

Correct Answer: D