The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur.
Which of the following will assist the project team with building the schedule?

A.
Task sequencing
B. Task predecessors
C. Task dependencies
D. Task prioritizing

Correct Answer: B

Explanation:

Explanation:
A predecessor activity is one that comes before another activity. A successor activity is one that comes after the activity in question.