Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?
A. Supply Ann with the requested tablet.
B. Have Ann submit a change request.
C. Provide Ann with a copy of the project management plan.
D. Inform Ann that she will receive what has been authorized.
Which of the following steps should the project manager take NEXT?
A. Supply Ann with the requested tablet.
B. Have Ann submit a change request.
C. Provide Ann with a copy of the project management plan.
D. Inform Ann that she will receive what has been authorized.