CompTIA Project+ PK0-004 – Question593

A customer-requested change has been denied by the CCB.
Which of the following should the project manager do NEXT?

A.
Halt project work until a meeting with the customer and the project sponsor takes place.
B. Update the project issues log.
C. Report the denied request to the customer and proceed with project work.
D. Reestablish the project baselines.

Correct Answer: C